Important MCQ questions for GATE, ESE Engineering Service Examination, IES, PSU Examination and Study Material For Electrical and Electronics Engineering in Circuit Theory, Network Theory, Material Science, Power System, Control System, Measurement, Power Electronics, Transformer and Electrical Machine, Control System, EMT, Power Electronics, Microprocessor and Communication System.
Saturday, December 28, 2013
Friday, December 27, 2013
SUB-STATION SPECIFICATION
1 Switching Surge and Power Frequency Over Voltages: The 400 kV system switching surge
over voltage and power frequency over voltage shall be limited to 2.5 p. u. and 1.5 p. u. respectively. The
initial value of temporary over voltages could be 2.0 p. u. for 1-2 cycles.
2 Overall Fault Clearance Time: Overall fault clearing time may be designed preferably less than
100 m sec. for 400 kV, 120 m sec. for 220 kV and 160 m sec. for 132 kV levels under comparable
conditions.
3 Duty Cycle of Circuit Breakers: The duty cycle of CBs installed in 420 / 245 / 145 kV System of
the Concessionaire shall be “O-0.3 sec-CO-3 min-CO”. The Surge Arrester shall be suitable for such
circuit breaker duties in the system.
4 Degree of Protection: The degree of protection for enclosures of the Control Cabinets, Junction
boxes and Marshalling Boxes, panels etc. shall as under:
i) Installed Outdoor: IP- 55
ii) Installed Indoor in air conditioned area: IP-31
iii) Installed in covered area: IP-52
iv) Installed Indoor in non air conditioned area where possibility of entry of water is limited: IP-41.
v) For LT Switchgear (AC & DC distribution Boards) : IP-52
5 General Electrical Clearances: Inter equipment arrangement and distances – bay length, bay
width etc. shall be maintained in accordance with the reviewed design of Single Line Diagram (SLD) and
General Electrical Lay-Out (GELO) of the substation.
Subscribe to:
Posts (Atom)
Topics
- Important MCQ Question
- PSU Questions
- Power System
- RPSC Lecturer Technical Education Department Exam 2014
- UPSC
- Electrical Machine
- PSC
- IES
- ESE 2011
- General Ability Test
- Power Electronics
- Circuit Theory
- DLB AEN 2016
- RPSC Lecturer Technical Education Department Exam 2011
- Electrical Measurement and Instrumentation
- IIFT 2013
- ESE
- Engineering Services Examination
- General Studies
- Interview
- IAS Mains
- EMT
- Important Days
- Optional Subject
- Control System
- Network Theory
- ISRO Scientist C SC- 2013
- Civil Services Mains
- CUT OFF
- IES/ESE 2008 Objective Paper 2
- Question Paper
- Analog Electronics
- ESE 2013
- PSU GATE Cut Off
- Signal And System
- Syllabus
- IES/ESE 2006 Objective Paper 2
- IES/ESE 2011 Objective Paper 2
- IES/ESE 2015 Objective Paper 1
- ISRO Scientist C SC-2014
- RBI Manager Technical PY 2015
- Computer
- Constitution
- Electrical Interview Questions
- Essay
- GATE 2012
- General Science
- IES/ESE 2001 Objective Paper 2
- IES/ESE 2002 Objective Paper 2
- IES/ESE 2003 Objective Paper 2
- IES/ESE 2004 Objective Paper 2
- IES/ESE 2005 Objective Paper 2
- IES/ESE 2007 Objective Paper 2
- IES/ESE 2008 Objective Paper 1
- IES/ESE 2009 Objective Paper 2
- IES/ESE 2010 Objective Paper 2
- IES/ESE 2012 Objective Paper 1
- IES/ESE 2012 Objective Paper 2
- IES/ESE 2013 Objective Paper 1
- IES/ESE 2014 Objective Paper 1
- UPSC-CPF-2007